Signing of the Protocol of Agreement between ECCAS and AfDB to finance the institutional and regulatory framework for electricity in Central Africa
Libreville (Rep. Gabonese), 19 October 2021–The President of the Commission of the Economic Community of Central African States (ECCAS), his Excellency Ambassador Gilberto Da Piedade Verissimo and the Country Manager, of the Gabon National Office of the African Development Bank Group (ADB) his Excellency Robert Masumbuko have proceeded to sign the Protocol ..
Libreville, Gabonese Republic, 19 October 2021–The President of the Commission of the Economic Community of Central African States (ECCAS), its Excellency Ambassador Gilberto Da Piedade Verissimo and the Country Manager, Gabon National Office of the African Development Bank Group (ADB) Excellency Robert Masumbuko signed the Memorandum of Understanding for the financing of the Project to Support the Development of the Institutional and Regulatory Framework for Electricity in Central Africa (PADCRE).
The objective of the project is to promote and strengthen the governance and sustainability of the electricity sector in the Central African region through the development of an effective, uniform and transparent regional institutional and regulatory framework that will enable the identification and establishment of clear strategies, policies, principles, rules, processes and standards to be adopted by stakeholders in the sector.
The project has four components:
- Development of a regional energy policy and an Energy and Social Management System (ESMS) and strengthening of the regional institutional framework for renewable energy and energy efficiency;
- Development of the Regional Interconnection Code and production of the Energy Information System of the Energy Pool of Central Africa (PEAC);
- Operationalisation and improvement of the new regional regulatory framework and
- Project management and coordination.
Project cost is 4,993,088 UC or 3.985.163.284 XAF and the countries benefiting from this donation are: Angola, Burundi, Cameroon, the Central African Republic, the Congo, Gabon, Equatorial Guinea, the Democratic Republic of the Congo, Rwanda, Sao Tome and Principe and Chad.
The duration of the project is 3 years. It runs from 19 October 2021, date of signature until 31 December 2024
The project's stakeholders are: the ECCAS Commission, the Permanent Secretariat of the PEAP, the Regional Commission for the Regulation of Electricity in Central Africa (CORREAC), the Centre for Renewable Energy and Energy Efficiency in Central Africa (CEREEAC), the Ministries responsible for Energy/Renewable Energy/Foreign Affairs/External Relations of ECCAS Member States, National Electricity Societies, Privateers and NGOs to name but a few.
It should be noted that this signature is the result of a process that follows:
– 5 February 2021: Transmission by the ECCAS Commission of the concept note of the PADCRE project to the AfDB;
– 26-28 July 2021: Organization of the Project Evaluation Mission (CECAS, AfDB);
– September 8, 2021: Project negotiations (CECAS, ADB);
– September 30, 2021: Approval of the project by the AfDB Board of Directors;
– 19 October 2021: signing of the Don's agreement by the Chairman of the ECCAS Commission and the Country Manager, Gabon National Bureau of the AfDB Group.